Skip to content

Cookie settings

Choose which kinds of cookies you allow. You can change your choice at any time via Cookie settings at the bottom of every page. Privacy statement

Necessary

Always on

Needed to log in, keep your cart and remember your choices. These are always on.

Which cookies?
  • weboke_sessie, weboke_klant, weboke_remember: your session and staying logged in
  • weboke_basket: your cart
  • wkBtwIncl: showing prices with or without VAT
  • wok_cookies: your cookie choice, 12 months

Measures which ad leads to a visit or order, so we do not pay for ads that do nothing.

Which cookies?
  • Google Ads via Google Tag Manager (_gcl_au, _gcl_aw), up to 90 days
  • OpenAI Ads, ads in ChatGPT
  • wok_aff: which partner referred you to us (affiliate programme), 60 days

All servers have been updated and are protected against the recent PHP vulnerabilities. Still seeing an older version number, such as 8.3.35? That is correct: the security fix is included, only the version number was not changed by CloudLinux.
4.6

Country and language

Each country has its own site, with prices and VAT for that country.

View

Calculating working days between two dates, excluding public holidays

How many working days do you have for a task? When does a ten working day payment term expire? Simply subtracting the dates also counts weekends and public holidays. There are special functions for that.

Working days between two dates

  1. Put your public holidays in a list, in the example in F3:F10 (New Year's Day, Easter, King's Day, Liberation Day, Ascension Day, Whitsun and Christmas).
  2. If the start date is in B3 and the end date in C3, type in D3: =NETWORKDAYS(B3,C3,$F$3:$F$10).
  3. Drag the formula down. The dollar signs keep the public holidays list in place.
NETWORKDAYS with a list of public holidays
NETWORKDAYS (1): from 19 April to 14 May 2027 there are 17 working days

In the example: from Monday 19 April to Friday 14 May 2027 there are 20 weekdays. King's Day and the two public holidays in the week of 5 May drop out: 17 working days.

A date a number of working days ahead

The final payment date, ten working days after the invoice date in F2: =WORKDAY(F2,10,Feestdagen!$A$2:$A$10). Give the cell the Short Date format.

A different working week

Do you, for example, work from Tuesday to Saturday? Then use NETWORKDAYS.INTL. The third part is a seven character code for Monday to Sunday, with 1 for a day off: =NETWORKDAYS.INTL(B3,C3,"1000001",$F$3:$F$10) for days off on Monday and Sunday.

Pitfalls

  • NETWORKDAYS counts both the start and end date. If you want "the number of days in between", subtract 1.
  • If the dates are stored as text, you'll get #VALUE!. See Dates that come in as text or have day and month swapped.
  • In the formula bar, Euro-Office sometimes places an @ before the public holidays range (…,@$F$3:$F$10). That's part of how Euro-Office displays the formula, the result is simply correct.
  • Ordinary calendar days between two dates: =C3-B3, with the Number format.